
EXCITING DISCOVERIES IN MONTEREY
Previously unknown
painted wall decorations have recently been uncovered at the Royal
Presidio Chapel of Monterey to the surprise of preservation
architect Anthony Crosby and his team. Crosby reports:
As of February 7, 2008, we have
confirmed that there are remains of four distinct dado schemes
which date prior to 1858. We willl probably be able to document and
interpret two and perhaps three of them. The fourth, which was probably
the second scheme, is not defined at all except as a separate layer and
color.
The earliest dado pattern, a banded
border above a diamond pattern, rendered in various shades of
red, rose and pinks, is associated with Corinthian columns which
supported a three centered arch that appears to define the sanctuary
area.
We have
also clearly identified two different faux stone patterns in the
original window reveals and also on the interior walls surrounding the
windows. The original windows were identified and masonry fill,
that was added in 1858, was excavated and the remaining details
documented.
We are
reasonably sure at this point that the earliest scheme dates from
before 1810 and possibly from 1794 when the chapel was completed. Some
of the details of the early scheme, which was very well executed, are
similar to what we know of the early scheme at Mission Dolores.
The investigation and documentation of
the interior decorations has also led to the irrefutable conclusion
that the present portadas of the 1858 transepts that earlier provided
access to the sacristy and baptistery, both of which were demolished
with the construction of the transepts.
We are not sure of the
relationship of the earliest scheme and the portadas, but hopefully
that is one of many questions that we will be able to answer. It also
appears that there was probably an arch spanning the nave and which
separated the nave from the sanctuary, again similar to that at
Mission Dolores and other missions.
This is definitely a work in progress
and we continue to try to answer as many questions as possible. The
overall project at the chapel consists of seismic strengthening, stone
conservation, landscape rehabilitation, masonry repair and interior
rehabilitation and it is a construction zone at this point.
For a more detailed report (pdf
format) on these recent discoveries at Monterey’s Royal Presidial
Chapel, with color photographs, CLICK HERE.
2/08
RECENT
CONSERVATION WORK AT MISSION SAN MIGUEL
--by Anthony Crosby
In December 2003 Mission San Miguel Arcangel was rocked by an
earthquake that resulted in the closing of the mission buildings to the
public. During the past four years work has been undertaken to repair
and seismically strengthen the east convento wing, which was the only
part of the convento that survived relatively intact into the 20th
century. The third phase of the repair of the east convento was
completed last year and currently a temporary church, the mission gift
shop and the museum are open.
In the meantime studies have been
underway to determine the most appropriate approach to preserving
the church, the sacristy and the remaining parts of the complex,
including engineering studies, an initial condition assessment of the
interior decorations, and an historic structure report, partially
funded by a Getty Grant and currently being developed incorporating
students from Cal Poly and California State at Monterey Bay.
Many of
these studies continue, and beginning in March 2008, the
preservation of
the original interiors enters a second phase with additional analysis,
testing and pilot treatments – this next phase will continue on site
over the next two to three months with two teams working, one
addressing the decorative plasters and another team addressing the
decorative and structural wood. At the completion of these studies, it
is anticipated that the comprehensive conservation of the important
interiors can be planned.
Analysis of the overall building and site conditions, such as the
effects of ground moisture on the 6-feet thick adobe walls, the site
hydrogeology, and the potential of continuing damage of highway and
rail traffic continue as well. In conjunction with the historic
structure report additional historical research will concentrate on the
evolution and changes in the mission complex, the development of the
architecture at San Miguel and an analysis of the authentic interior
decorations from the perspective of an art historian.
For a pdf version of this article which includes photographs of
conservators and students at work, please click
here.
3/08

Retrofitting History:
Mission San Luis Obispo de Tolosa
by Hilary Grant
(reprinted
from JOURNAL PLUS, March, 2008)
|

|
Mission San Luis Obispo was founded in 1772, the fifth of 21 California
missions, by Friar Junipero Serra. Today it is a large and active
parish and a familiar place for summertime festivals, street concerts,
and meetings with friends. This year (2008) marks an important and much
needed chapter in the building’s history -- a complete
retrofitting. “No engineer will tell you that the present Mission
is earthquake safe,” says John Fowler, who is serving as project
manager and capital campaign director for the entire $2.8 million
job. “And while there is no reason to believe there’s any
imminent danger -- the present structure has been around for more
than 200 years and there was only minor cracking with the San
Simeon quake in 2003 -- any building could come down with the right
earthquake.”
To ensure that the likelihood of such a disaster won’t happen to the
Mission -- for many, this compound and the narratives behind it
represent both the centerpiece and soul of San Luis Obispo -- Fowler
will start taking bids from general contractors this month. It’s
part and parcel of adhering to a SLO city mandate, which states
that all non-reinforced masonry structures in San Luis Obispo
must be seismically strengthened no later than July 1, 2010. “The
City hasn’t said what their next step will be if that’s not done,” says
Fowler. “ But we’re assuming that closure is high on the list.”
Once a contractor is selected, the Mission retrofit is scheduled to
begin quickly in April, with the building then closed to the public on
weekdays for about six months. Saturday and Sunday Masses are slated to
continue, although a massive cleanup will be needed every Friday and a
certain amount of lighting will most likely be temporarily removed or
improvised. Whether the Mozart Festival will have its usual venue
here this summer, as well as the building still being available for
wedding ceremonies, remains an unknown.
While the actual retrofit seems uncomplicated in theory --
installing new roof sheeting on top of the existing sheeting,
then securing that fresh cover with concrete beams -- the project
offers its own unique set of challenges. “Given that the Mission
has been around for a few hundred years, many repairs and alterations
have been done,” explains John Fowler. “And with brick, adobe,
and wood all used in different parts of the building at different
times, the walls are thicker in some places than in others. So, the
most difficult part for our team has been to take all of these
variations of craftsmanship and materials and try to tie them all
together to make the retrofit work.” Another huge challenge is
this -- there are no original blueprints on the Mission.
Consequently, one of the first things Fowler did was hire Architectural
Resources Group, a San Francisco-based historical architectural
firm. That firm, one of the largest of its kind in the state,
then produced a Historical Structures Report (HSR). The HSR proved
crucial when it came to figuring out how the Mission came to be; when
and what repairs were done before the upcoming retrofit, and what the
existing structure is like today.
“”I’m still learning what a complex undertaking this all is,” says Fr.
Russell Brown, who only completed seminary and entered the priesthood
in 2004. In addition, Father Russ has served as the Mission
pastor -- his first pastoral assignment -- for less then two
years. “I was pretty newly ordained when one of the most
complicated parishes in our diocese was offered to me. There was
not a long list of applicants for the job! I do recall talk of an
earthquake reconstruction project when I was interviewed, but it wasn’t
until I arrived here that I understood the full picture,” he
continues. “This is not just a little shoring up, but requires a
contractor, and electrician, engineers, architects, archaeologists,
fire inspectors and on and on. Now, for all that entails, I’m
surprised to some degree that I really do find the whole project
interesting.”
“There’s no handbook for this -- we’re learning as we go,” explains
John Fowler. “But getting the HSR done was the first step to this
effort. You must know everything you possibly can about a
building like this before you can begin to make additional
changes.” Having Fowler as project manager, says Fr. Russ, has
been an invaluable asset. “While I’m ultimately responsible for
everything that concerns the Mission, John’s expertise is absolutely
crucial to the retrofit here,” he says. “He allows me to focus
more on the pastoral needs of the church, which always more than fills
my day.” Fowler certainly has the requisite credentials for the project
-- indeed, if anyone can bring this plan in on time and on budget, he
can. A certified public accountant by profession, Fowler also
served as project manager for the recently finished $10 million Mission
College Preparatory addition, and also holds the same title for the
ongoing renovations at Mission San Miguel Arcangel, just north of Paso
Robles. Under Fowler’s direction, the SLO Mission museum and gift
shop have already been completely retrofitted.
Despite all the formidable challenges inherent in this particular
seismic upgrade, John Fowler and Fr. Russell say that they’re glad to
be active participants. “Everyone is interested in missions
and their place in California history, so that makes this project great
fun,” says Fowler. “Plus, we get donations and visitors from
around the world. We also attract the best engineers and
architects -- and I get to work right alongside them.” Adds Fr.
Russ, “I’m very happy to be here right now. I’ll do what I can to
keep the parish together and spiritually fed while we achieve this
mandate. We’ve been serving this community for 235 years, and the
work we accomplish now will secure our Mission for centuries to come.”
Funds are still needed to complete the retrofitting of Mission San Luis
Obispo de Tolosa. Donations can be made in cash, check or in the
form of pledges that may be paid in three to five years. For more
information, visit <www.OurCommunityOurMission.org> or call John
Fowler at (805) 550-8639.

MISSION SAN JUAN CAPISTRANO:
Preservation of Serra Chapel Underway

The Team will apply a pigmented limewash in the coming
weeks,
formulated to match the east wall of the Serra Chapel.
The Team hired a professional pest control company to
treat the Mission for termites in late December. Two parts of this
treatment effort were
implemented, including carrying out a non-invasive "in-ground"
treatment for subterranean termites. The second part was more labor
intensive, with the Team tenting and fumigating the Gift Shop, South
Wing, Serra Chapel, Rectory, Kindergarten classrooms, and Mission
Administrative Building. It was determined that prior to carrying out
the wood treatment within the Chapel, it would be best to fumigate for
termites, ensuring that they did not continue their damage to new
preservation work.
There are bound to be visual
impacts as a result of
this project, not to mention disruption. However, in order to ensure
the Chapel remains viable for the next one hundred years, it is
imperative that the Mission carry out this work despite the impact.
The Historic Mission staff is committed to carrying
out the entire conservation of the Serra Chapel within three years.
Raising $1.5
million will expedite the work and return the Chapel to its proper
uninterrupted tradition of worship.
During 2006, the Serra Chapel Conservation Project
will include
initiating the following priorities:
1. Consolidating, in-painting, and cleaning the
interior decorative wall paintings; and,
2. Conserving the golden retablo, and repairing the
badly deteriorated
wooden corbels and beams; and,
3. Conserving the first of fourteen paintings
depicting the Stations of
the Cross, Station IV: Jesus Meets His Mother; and,
4. Carrying out conservation work on a second altar
candlestick; and,
5. Refurbishing the 1920's pews.
More information and photos appear on Mission San Juan Capistrano's webpage
East
Hall, Southwest
Corner
Same corner of ceiling, after
Ceiling before
Restoration
restoration
Another program at Mission San Juan Capistrano focuses on
artifacts conservation. Storage of historical artifacts in
clean, secure, and environmentally-monitored facilities is
crucial to their continued survival. Mission San Juan
Capistrano has recently received two prestigious
grants to improve its storage facilities, one of $9000 from the
California Missions Foundation and one of $5000 from the National
Endowment for
the
Humanties; work in this important area is going forward.
If you
are
interested in supporting the work for the Serra Chapel or the Mission's
artifacts conservation program and would like
to make a gift , contact Ellen Pierce, Mission
Development Manager, at (949) 234-1375.
10/06
HOME | Archive | Articles
& Book Reviews | Bibliographies | Conference | Directory
| Events | Illustrated
Glossary | Journals | Links | Publications
|
All rights reserved. Webpage © 1997-2008
CMSA.
Last updated 28 February 2008